TOP3: How to control the costs of a demanding project

26.11.2026 – Ilkka Kallioinen, Department Director at Granlund, identifies three areas that should be taken into account in the cost control of data centers and other demanding projects. What can be done to control costs?

The larger and more demanding the project, the more a cost specialist’s expertise can improve the project’s productivity and risk management. In my experience, a cost specialist can often provide help in three areas that enable the successful cost control of the project:

1. Compiling accurate and sufficient initial information

It is important for all parties to know what kind of initial information the cost estimate is based and how lack of information affects the reliability of the estimate. The first cost estimate should already be made with the most accurate information possible and be based on quantities.

It is also important to document the initial information for the cost estimate accurately, so that in later phases it is clear from which material the cost has been calculated.

2. Information flow within the project

Changes cannot be avoided, and what is more important is how changes in design and scheduling are communicated within the project. Even the best initial information will not be enough if the cost specialist is unaware of changes in design decisions or delays in permit matters.

It is impossible to control costs if the cost estimate is just a single amount on a single row. The quantity-based approach increases transparency in the estimate, and more detailed cost data creates opportunities for control. Cost data already shows at an early stage where the largest costs will be.

It is impossible to control costs if the cost estimate is just a single amount on a single row.

3. Determining the publication timing and method of the preliminary cost estimate

The first cost estimates of projects persist for a long time. If a preliminary cost estimate is needed quickly, for example for a presentation or budget meeting, the limitations of the calculation and the price risks must be carefully recorded.

Basing the estimate on a databank compiled from previous projects helps when making early quantity and cost estimates. By comparing estimates against actual cost data from previous projects, more accurate cost estimates can be made even with incomplete initial information. However, data analysis requires the expertise of a cost specialist: the benchmark data must be adapted to suit the project.

How does Granlund’s databank work?

Granlund’s databank is based on quantity and cost data that has been collected over decades.

If the calculation is being done about, for example, a 10,000 square metre school building, we will use the hundreds of school projects in our databank for the cost estimate.

The databank serves as a source of information, but its real benefits are ensured by specialists. Cost estimators select appropriate benchmark projects and make a transparent cost estimate based on them.

Communication can resolve many cost control crises

In my opinion, what is most important regarding the above-mentioned areas is effective communication in cost calculation and quantity surveying using language that clients, contractors and equipment suppliers can understand. In addition to being able to use Finnish and English, this requires the ability to understand the client’s perspective.

Clients. Communication with the client and the client’s representatives is especially important at the beginning of the project and in situations where there are changes. A lot happens between the planning of the project and the planning of the implementation. When information flows directly to cost specialists, we are able to produce real-time cost information during all phases of the project.

Contractors. Many of our cost specialists have a background in contracting. This means that we understand how contractors think and are able to calculate quantities and predict future contract prices. For example, we know how contractors calculate risk or margins.

Suppliers. For a cost specialist, it’s important to stay up to date with market prices. We also carry out cost calculation and quantity surveying for contractors, which means that we are in daily contact with suppliers, know the current prices and understand which products have the greatest variation in budget prices.

The cost specialist adapts to different roles with different clients

It is important for cost specialists to adapt flexibly to different roles, which means that the focus of cost calculation also shifts according to the project:

In alliance projects, we act as a cost specialist employed by the client. For example, in the Laakso Joint Hospital alliance, cost control has been part of the project since the beginning, but our role has gradually shifted, becoming more focused on the duties of a cost specialist, which ensures that cost targets are fair and, when achieved, deliver the planned value to the client.

Construction companies need quantity surveying and preliminary prices to support their tender calculation. Many of our cost specialists have completed their most important “higher education” in the world of contracting, thanks to which we have extensive experience in project cost estimation and the ability to operate under pressure within tight schedules.

Many of our cost specialists have completed their most important “higher education” in the world of contracting, thanks to which we have extensive experience in project cost estimation and the ability to operate under pressure within tight schedules.

In data center projects, cost specialists ensure that the cost estimate is realistic from the outset and updated in real time. Our cost specialists monitor the often rapidly changing, technical data center environment. In addition to normal costs, a major factor affecting costs is the availability of skilled labour: assessing this requires knowledge of the local market and competitive situation.

In international projects, the role of the cost specialist includes taking into account local practices and regulations. In Finland, for example, the legislation on collective agreements guides how installation work is carried out and how contract prices are calculated. Understanding Finnish practices helps international clients comprehend Finland’s country-specific characteristics.

Principles for successful cost control

Although there are differences in operating environments, successful cost control is usually based on the same principles:

1. The first cost estimate is already made in a quantity-based way. About 80% of a project’s costs are determined during the initial phase of the project, so it’s a good idea to create the foundation for cost control carefully and in sufficient detail.

>> We can carry out the initial cost calculation at the same level of accuracy as that of the calculations made during the implementation phase.

2. The databank is used as the basis for cost calculation. In cost calculation, we rely on a calculation library accumulated over nearly 20 years. In fact, we are pioneers in using the same kinds of quantity surveying and cost calculation methods as contractors.

>> For competition reasons, contractors cannot share their calculation data with clients. We can.

3. Cost control is based on details. Quantity-based calculation always takes into account the distribution of costs all the way from pipes to large equipment. If necessary, we are able to look at costs at a very detailed level, which makes the costs transparent.

>> All successful cost control projects rely on two pillars: a quantity-based databank and its expert use.

In what areas can quantity-based data be used?

The use of the databank is not limited to cost control. Quantity data and its customisation can be used, for example, in the following:

• The guidance of carbon footprint and low carbon solutions

• 4D scheduling

• Project management

• Logistics procurements

• Takt production, when the project is divided into different takt zones.

Even though cost calculation is expert work, we can still take advantage of data, automation and artificial intelligence to enhance our ways of working.

Get in touch!

Ilkka Kallioinen

Department Director, Cost Management
Granlund Oy

Marco Savolainen

Department Director, Data Centers
Granlund Oy

Read more blog posts

TOP3: How to control the costs of a demanding project

26.11.2026 – Ilkka Kallioinen, Department Director at Granlund, identifies three areas that should be taken into account in the cost control of…

Blog post

What is required of a local PMC partner for data center projects?

09.11.2026 – As the complexity of a project increases, there must be a party that manages the project as a whole. Our…

Blog post

Great expertise drives Granlund forward

06.08.2026 – Competent and motivated employees are crucial for Granlund’s future growth. According to Granlund’s CEO Pekka Metsi, acquisitions bring in highly…

Blog post
Veikko Martiskainen, Granlund Oy

Fast track delivery for data centers in Finland

04.08.2026 – An experienced and competent local partner can help ensure data centers in Finland are commissioned on schedule and on budget.

Blog post

A new law gives wind park owners better use of data

21.05.2026 – Granlund’s unique data analysis service helps wind park operators better understand and optimize their assets.

Blog post

How to make your data center permitting flow smoothly 

23.04.2026 – Mikko Reinikainen, Architect and Principal Designer at Granlund explains the art and science behind successfully getting permits for a new…

Blog post

How to secure power for data centers

17.09.2025 – Power security is essential for data centers. Our experts in Finland and Sweden explain what to look for when planning…

Blog post

AI can revolutionise the built environment, with a little help

09.05.2025 – AI is already beginning to transform the built environment. What is Granlund’s role in this revolution, and what does it…

Blog post

How can a construction manager make it easier to implement an international project in Finland?

15.04.2025 – Granlund’s construction management experts help international industrial and data center operators throughout the project, from selecting the location to site…

Blog post

How can you measure the impacts of construction on biodiversity loss?

18.03.2025 – As much as a third of biodiversity loss is the result of construction. In our pilot project, we tested biodiversity…

Blog post

Subscribe to our newsletter

Be among the first to hear about the latest news and trends relating to Granlund and the real estate and construction sectors.

Search